Table of Contents Table of Contents
Previous Page  279 / 536 Next Page
Information
Show Menu
Previous Page 279 / 536 Next Page
Page Background

and formalising the storage area operating instructions.

BNI 49must also be vigilant with regard to themanagement

of decommissioning wastemovements and storage areas

which have led to the notification of two significant events.

The centre’s organisation of transport management was

considered generally satisfactory.

The CEA has also again notified events concerning the

monitoring of gaseous discharges from the installations.

One event in particular revealed that the steps taken by

CEA to ensure compliance with the resolutions regulating

the discharges from the centre had not been carried out

exhaustively and with the necessary rigour.

Operation of the BNIs

ASN considers that the physical upgrades necessary to

start decommissioning of the Ulysse reactor have been

carried out. In 2015, ASN examined the updating of the

operating baseline requirements, whichwas a prerequisite

for decommissioning.

The arrival of a new industrial operator to run the Stella

facility represents a potential risk for the licensee who

must be vigilant with regard to the management and

monitoring of this activity. The operations to remove legacy

effluents fromBNI 35must also be continued in compliance

with the time frames of resolution 2014-DC-0441 of

15th July 2014.

The OSIRIS reactor was shut down at the end of 2015.

The prospect of this shutdown led to the updating of the

decommissioning plan and the defining of final shutdown

preparation operations which are to start in 2016 in

order to benefit from the skills and experience of the

operating team in place.

ASNnotes that the BNI 49decommissioning operations are

proceeding to the set schedules. The level of subcontracting

is particularly high on this BNI. Control of the operations

performed by the outside contractors is therefore an

important issue.

In BNI 50, ASNhas observed that the plannedmeasures

to improve the performance and traceability of technical

verifications and periodic tests have been implemented.

The removal from storage work in progress on BNI 72

is technically well controlled, but the effectiveness of

monitoring outside contractors still needs to be improved.

ASNunderlines that management of the replacement of

high-activity sources of BNI 77 in2015 led tononcompliant

storage in the centre’s installations lasting several weeks

and late notification of the fact. The CEAmust examine the

internal causes of this situation and the lack of transparency.

The Orphée reactor licenseemust bolster its organisation

for the planning and tracking of performance of

verifications and periodic tests. ASN’s inspections have

shown compliance with the planned actions and the

conditions for restarting after the two significant events

concerning the handling of fuel elements which occurred

at the end of 2014.

The CIS bio international plant in Saclay

ASN considers that the operating safety performance of

CIS bio international must be significantly improved.

ASNconsiders that the effortsmadebyCISbio international

to reinforce its integratedmanagement system, its human

resources and operatiing conditions that promote

cross-functionnality put in place in 2015, have not

yet produced lasting concrete results. The verification

of the conformity of operations, compliance with the

baseline requirements of the installation and those of

the regulations for the implementation of modifications

must be reinforced.

Further to noncompliance with the ASN prescriptions

issued after the periodic safety review, ASN applied

coercive administrative policing measures in  2014

and  2015. Formal compliance notices were sent first

of all, then, further to the failures to comply with these

notices, padlocking procedures were applied to oblige

CIS bio international to equip the installation with

automatic fire extinguishing systems in accordance

with predetermined deadlines. Pending finalising of the

works whose deadlines were not met, ASN prescribed

compensatory measures to step up control of the fire

risk through a resolution of 14th April 2015.

A large amount of work contributing to improving

safety, which has been in progress for several years, is not

completed. As a general rule, the large-scale undertakings

of CIS bio international are never completed within

reasonable time frames.

A new laboratory has been put into service and the

automatic fire extinguishing systems are partially installed

and functional. Complementary studies concerning

the consequences of accident situations remain to be

finalised.

The stated time frames for performing the actions defined

further to inspections and events are exceeded too

frequently. The deviations observed during inspections

and the predominance of organisational and human

factors in the causes of events reveal persistent weaknesses

in operating rigour, in intervention processes and in

assessing the importance of the deviations. Equipment

maintenance must be improved in particular.

ASNwill be attentive to CIS bio international’s compliance

with prescriptions, the meeting of its commitments and

its improvement of safety in operation. ASN expects an

increase in the effectiveness of the current organisation

and the industrial approach implemented. Consequently,

it will keep the facility under tightened surveillance

in 2016.

ORLÉANS DIVISION

279

CHAPTER 08 :

REGIONAL OVERVIEW OF NUCLEAR SAFETY AND RADIATION PROTECTION

ASN report on the state of nuclear safety and radiation protection in France in 2015