rigour, application of and compliance with instructions.
In effect, several significant events in 2015 again revealed
shortcomings in this respect, their main consequences
being containment losses. ASNmoreover observed that the
monitoring of outside contractors is not always satisfactory,
despite the licensee’s commitment, which has already
been pushed back, to deploy the Areva group’s directive
at the end of 2014.
For the TU5 facility, 2015 started with clean-out work to
allow its restarting following the event of December 9th
2014 involving a significant leak of uranyl nitrate, which
was limited to the premises of the installation. ASN
conducted an inspection to verify the licensee’s repair
work before the facility was put back into service. On
the basis of its findings, ASN asked Areva to improve the
management of the prerequisites for return to service.
ASNhas moreover started examining the periodic safety
review file for this installation. Once the examination is
completed, ASNwill state its position on the continuation
of operation of these installations at the end of 2016.
For the W facility, the start of 2015 was marked by
the entry into service of the new hydrofluoric acid
storage area, which went smoothly. The examination
of this modernisation work led ASN to update all the
technical requirements applicable to this ICPE, which is
classified Seveso high-threshold, through its resolution
of 6th January 2015.
With regard to the new emission unit (EM3) whose
entry into service has been prescribed by ASN for 2018,
examination of the file began in 2015 along with the
preparation of the worksite for work to start at the end
of 2015. This new unit will meet the safety requirements
set by ASN following the Fukushima Daiichi nuclear
accident.
Areva NC (Formerly Comurhex)
Fluorination plant in Pierrelatte
ASN considers that the facilities situated within the
perimeter of BNI 105 are operated with a satisfactory
level of safety.
Particularly noteworthy in 2015 was the examination
of the request to extend operation of the Comurhex I
plants until the end of 2017. This request from Areva
stems directly from the fact that construction of the new
Comurhex II plants is well behind schedule. This extension
has been framed by ASN CODEP-LYO-2015-024792
resolution of 30th June 2015, which set out the main
reinforcement works for these plants. On 11th August
2015, ASN carried out an unannounced inspection to
find out whether these principal improvements had
been effectively carried out, at the end of which it asked
that the layout of a newly installed mitigation system
be improved.
ASN therefore remains attentive to ensuring that sufficient
rigour in the operating and maintenance procedures
for these plants is maintained. This latter point must
be put into perspective with the ongoing renewal of
personnel skills which remains a subject of attention for
ASN, particularly with a view to the transition between
the facilities of Comurhex I and those of Comurhex II
in the years to come.
With regard to the environmental aspects, the discharge
resolutions of BNI 105 were revised in 2015 by ASN
resolutions 2015-DC-0496 and 2015-DC-0497 of
27th January 2015.
ASN also observed an unsatisfactory situation in the
management of the conventional waste areas of BNI 105.
The licensee reacted promptly and deployed a plan of
action to restore conformity.
Eurodif Georges Besse -
Uranium enrichment plant in Pierrelatte
The last rinsing operations were continued until October
2015, under conditions that ASN considers satisfactory.
Since the end of these operations, there is no longer any
chlorine trifluoride (ClF
3
) in the facility.
Due to technical difficulties, particularly concerning the
qualification of new equipment items, the operations to
hydrolyse and introduce air into the cascade did not start
until 2015 and will continue in 2016.
ASN moreover authorised the operations to hydrolyse
and introduce air into the DPR unit and the final
shutdown of the units of annex U for treating substances
extracted from the diffusion cascade. It is currently
examining the hydrolysis authorisation application for
the annex U systems. Following all these operations,
which will have eliminated the majority of the source
term, the plant will be in a surveillance phase until the
first decommissioning operations are started.
In accordance with the Decree of 2nd November
2007, the licensee submitted its final shutdown and
decommissioning application for the installation at the
end of March 2015. Examination of its admissibility
revealed that further information was required before
the examination could proceed. These shortcomings
concern general aspects in the decommissioning strategy
adopted by Eurodif Production, more particularly in the
management of radioactive waste and the description of
the initial and final states of the installation.
LYON DIVISION
257
CHAPTER 08 :
REGIONAL OVERVIEW OF NUCLEAR SAFETY AND RADIATION PROTECTION
ASN report on the state of nuclear safety and radiation protection in France in 2015




