With regard tomaintenance, ASNnotes that the refuelling
outage of reactor 2 was satisfactory on the whole, but
work monitoring must be further improved in order to
prevent the maintenance quality shortcomings detected
on some items of equipment.
The site’s organisation in the area of radiation protection
is generally satisfactory. ASN has nevertheless observed
deviations in the monitoring of devices used for radiation
protection checks and in the application of instructions
relative to risk identification and the associated protection
measures.
With regard to emergency situations, ASN notes that the
national emergency exercise carried out on 13thOctober
2015 was satisfactorily managed by the site, particularly
from the technical aspects, even if the quality of external
communication must be improved.
In the area of the environment, EDF provided ASN with
complementary information concerning the operation,
inspectionandmaintenance of the liquideffluent collection
and retention systems; ASN ensured that EDF continued
implementing the planned improvements in this area.
Labour inspection in the nuclear power plants
ASN continued its inspection actions concerning
subcontracting, situations of illegal lending of labour,
the working time of employees of EDF and of certain
subcontractorsandtheconditionsofhealthandsafetyduring
maintenance andconstructionwork. ASN’s oversight action
resulted in the improvement of the working conditions
of the operators on the Paluel 2 reactor condenser repair
worksite in order to meet the applicable requirements.
ASN also examined the circumstances of the fall of the
lifting beam for handling the steam generators on the
Paluel 2 reactor. On this subject, ASNasked that EDF and
the contractor companies involved continue the requisite
analysis and implement appropriate corrective action.
With regard to radiation protection, the inspectors
continued to check implementation of the Everest
initiative on the Flamanville site, an initiative that
significantly changes the conditions of access to controlled
areas and must still undergo operational adaptations.
ASN continued its inspections during work in hot
environments at the beginning of the reactor outage
periods: ASN considers that EDF must confirm the
practical feasibility of the envisaged response actions
should an accident involving a person or person occur
in certain poorly accessible areas.
Construction of the Flamanville 3 EPR reactor
After issue of the authorisation decree and the building
permit, construction work began on the Flamanville 3
reactor in September 2007.
A predominant part of the activities in 2015 concerned
mechanical assemblies, particularly the reactor main
primary system, the electrical installations and the
performance of the first startup tests (see chapter 12,
point 3.3). With regard to civil engineering, the
prestressing of the internal containment of the reactor
building and construction of the external containment
were completed in 2015. ASN carried out a specific
inspection of these operations, and examined worker
radiation protection, protection of the environment
and preparation for reactor operation.
ASN considers that the organisation implemented by
EDF remained satisfactory on the whole.
The work of introducing the principle components of
the main primary system into the reactor building and
then assembling them, which began at the end of 2014,
continued during 2015. This system contains the reactor
core and is thus of primary importance for safety. ASN
examined EDF’s monitoring of the outside contractors
involved in the assembly of the primary system, especially
Areva NP, the systemmanufacturer. ASN considers that
the cleanliness requirements are satisfied on the whole
and that EDF’s management of concomitant activities
conducted near items of equipment is generally adequate.
ASN notes the discovery and subsequent treatment in
2015 of several nonconformities that occurred during
welding of the equipment; ASN considers that EDF
must, in collaboration with the equipment manufacturer,
further the analysis of this issue.
With regard to prestressing of the internal containment
which began in summer 2014, EDF informed ASN of
further difficulties encountered during the tensioning of
a prestressing cable in February 2015. EDF suspended
the activities concerned as a precautionary measure
pending determination of the causes of the deviations
and preparation of a corrective action plan. EDF kept
ASN regularly informed of the deviations observed
during the prestressing activities. ASN adapted its
inspection of this activity accordingly, in particular by
conducting four specific inspections. ASN considers
that EDF responded appropriately to these deviations.
On completion of the inspection of the first startup tests of
the ventilation equipment and the continued tests of the
equipment installed in the pumping station, ASNconsiders
that EDF’s organisational setup for the preparation and
performance of the startup tests can be improved. More
specifically, EDF must be attentive to the rigour with
which deviations encountered during the startup tests
are dealt with in order to decide, among other things,
on the representativeness of the tests performed and
the acceptability of their results, while at the same time
integrating experience feedback for subsequent tests.
ASN will be attentive to ensure proper performance of
the preliminary tests which shall be followed by the
overall tests of the reactor systems.
CAEN DIVISION
235
CHAPTER 08 :
REGIONAL OVERVIEW OF NUCLEAR SAFETY AND RADIATION PROTECTION
ASN report on the state of nuclear safety and radiation protection in France in 2015




