Table of Contents Table of Contents
Previous Page  236 / 536 Next Page
Information
Show Menu
Previous Page 236 / 536 Next Page
Page Background

In view of the time frames announced by EDF for reactor

commissioning, ASN considers that EDF must remain

vigilant with regard to the preservation of the equipment

already installed, taking into account the worksite

conditions and the ongoing concomitant activities.

ASN examined the organisation put in place by the teams

responsible for future operation of the Flamanville 3

reactor, particularly for the production of the operating

documentation, preparation for arrival of the nuclear

fuel on the site and consideration of organisational and

human factors. ASN considers that the organisation

implemented by EDF in these areas is satisfactory.

ASN fulfils the labour inspectionduties on the Flamanville 3

construction site. In 2015 the inspectors continued to

check that the outside contractors working on the site

compliedwith the provisions concerning the safety rules

implemented; they drew attention in particular to the

impact of the startup tests, which involve powering up

systems or putting equipment under pressure.

Andra’s Manche repository

ASN considers that the condition and the operation of

the Manche repository facilities are basically satisfactory.

Andra must continue to reinforce the stability of the

repository’s cover and continue its efforts to eliminate

water infiltrations at the edge of the membrane intended

to ensure the water-tightness of the storage volume.

In accordance with the commitment made during the

last periodic safety review, Andra sent ASN an interim

review of the work carried out on the repository cover.

Lastly, Andra sent ASN a revision of the repository’s

on-site emergency plan.

ASN considers that Andra’s continuing measurement

of tritium using the methods of the study that began

in 2012 should lead to a better understanding of the

hydrogeological mechanisms involved.

As concerns the maintaining of the repository memory,

Andra must continue its work to prioritise the detailed

data with a view to proposing a new version of the

synthesis by 2016.

Ganil (National Large Heavy Ion Accelerator)

ASN considers that the Ganil licensee continues on

the whole to satisfactorily ensure the construction

work of phase 1 of the Spiral 2 installation, for which

the authorisation decree was published in 2012. The

way in which worksite monitoring is organised seems

well-founded and functional. During its inspections in

2015, ASN nevertheless detected shortcomings in the

performance of the tests relating to safety, whichwill have

to be supplemented. ASNconsiders that the licenseemust

improve its organisation for themanagement of low- and

very low-level radioactive waste produced on the site.

ASN continued its examination of the commissioning

application for phase 1 of the Spiral 2 project.

ASNcompleted the examination of the first periodic safety

review of the installation since it was commissioned in

1983. On completion of this process, ASN set technical

prescriptions that supplement the licensee’s commitments

to bring the installation into compliance with its baseline

requirements and the regulations in effect.

The Brennilis nuclear power plant undergoing

decommissioning

ASN considers that the conditions of safety for

continuation of the partial decommissioning activities

on theMonts d’Arrée site have proved to be sub-standard.

On 23rd September 2015, a fire broke out on the heat

exchanger decommissioning worksite, which was in the

final phase of clean-up at the time, resulting in activation

on the on-site emergency plan. The heat exchanger and

the effluent treatment plant decommissioning worksites

have both been suspended since then. ASNnotes that the

prior analyses and the way the fire risk for these activity

phaseswas specifically taken into accountwere insufficient.

ASN has asked EDF to undertake all the actions to review

all the organisational and humanmeasures implemented

to control the risks associated with hot work on the

decommissioning worksites as soon as possible.

The effluent treatment plant post-operational clean-

out and demolition worksite was interrupted several

times, notably after the fall of a rubble-sorting machine.

In addition to this, ASN verified compliance with the

commitments made by EDF at the end of the inspection

carried out in 2014 concerning the management of the

excavations area and compliance with the conditions

associated with management of contaminated water

on the site.

ASN has received the management plan for the land on

which the former effluent treatment station is situated

and has asked EDF to submit a new file with a view to

complete decommissioning of the installation.

1.2 Radiation protection

in the medical field

Radiotherapy

In 2015, ASN continued the two-year inspection cycle

covering all the radiotherapy departments in Normandy;

an annual inspection is maintained for the departments

with identified points requiring particular vigilance. The

inspections conducted in 2015 revealed the maintaining

of a real process to improve the rigour, organisation and

traceability of interventions and the implementation of

management systems to ensure the quality and safety

of treatments. Nevertheless, in spite of the increased

staffing in the majority of the radiotherapy centres, a

small number of the centres in Normandy still suffer

CAEN DIVISION

236

CHAPTER 08 :

REGIONAL OVERVIEW OF NUCLEAR SAFETY AND RADIATION PROTECTION

ASN report on the state of nuclear safety and radiation protection in France in 2015