Table of Contents Table of Contents
Previous Page  266 / 536 Next Page
Information
Show Menu
Previous Page 266 / 536 Next Page
Page Background

CEA Marcoule centre

ASN carried out 11 inspections of the Marcoule centre’s

two BNIs in 2015, one inspection of the projected

BNI Diadem, and two cross-cutting inspections. ASN

considers that safety management of the civil BNIs at

the CEA Marcoule centre is satisfactory on the whole.

The inspections of the centre showed ASN that the

on-site transport operations and monitoring of the site

environment were correctly organised and carried out

in 2015.

Preparation of decommissioning of the Phénix

reactor continued in 2015 with the carbonation of the

residual films of sodium of the secondary systemNo.1.

Decommissioning of the installation will be the subject

of a Decree in 2016. Shortcomings in the monitoring of

outside contractors were also noted during an inspection

conducted jointly with ASND concerning a shipment

of containers of waste between the power plant and a

storage facility of the Secret BNI of Marcoule.

ASN carried out tightened investigations of the Atalante

installation in 2015 following the occurrence of three

significant events between 2013 and 2015 concerning

the electrical power supply and the instrumentation and

control systems, in order to check that the licensee was

actively implementing the planned actions further to

these events. These actions focus more particularly on the

sizing of the electrical power supplies, their maintenance

and verification of the programming of all the general

services’ instrumentation and control controllers. ASN

will remain particularly vigilant regarding this subject

during the inspections and the examination of the BNI’s

periodic safety review.

On 12th November 2015, ASN issued a favourable

opinion on the draft decree authorising CEA to create

the Diadem BNI.

Centraco plant

ASN carried out eight inspections in the Centraco plant

in 2015. A highlight of the year was the restarting of the

melting unit authorised by resolution of 9th April 2015.

With regard to experience feedback, a significant event

involving the introduction of greasy scrap metal into

the melting furnace was rated level 1 on the INES scale.

ASN conducted a reactive inspection and observed that

the furnace had been shut down in compliance with

the applicable procedures and that the greasy parts had

been removed from the feeder circuit. Improvements in

personnel training and checking of parts to be melted

were requested by ASN and implemented to prevent the

recurrence of this event.

In early 2015, the incineration unit underwent a technical

shutdown during which the quench tower was replaced.

After observing some difficulties in the waste drum

introduction airlock, which had no impact on the safety of

the facility, incineration began functioning correctly again.

On a different subject, the licensee was unable to obtain

the renewal of approvals relating to certain categories of

ultimate waste within time frames allowing their removal

before exceeding the maximum authorised duration of

on-site storage, whichwas considered a significant event

rated level 1 on the INES scale. ASNexpects these situations

to be better anticipated.

Gammatec ioniser

ASN conducted an inspection of the Gammatec ioniser in

2015 and considers the level of safety to be satisfactory.

Improvements are however expected in themanagement

of modifications to the installation, the handling of

nonconformities and putting the personnel into simulated

situations during exercises.

Ecrin facility on the Malvési site

ASN carried out an inspection of the Ecrin facility in

2015 and considers that environmental monitoring is

satisfactory. 2015 saw the regularisation of the facility

by the Decree of 20th July 2015 authorising storage of

radioactive waste for a period of thirty years. ASN will

set prescriptions in 2016 to regulate the conditions of

transfer of liquid effluents andmonitoring of the facility’s

environment. These prescriptions constitute a prerequisite

for the facility commissioning authorisation which will

consist in development work to limit the impact of the

facility.

Gammaster ioniser in Marseille

ASN carried out one Gammaster inspection in 2015.

The licensee performed a sealed sources requalification

operation in 2015 with a view to extending their service

life by ten years. The result of this operation is positive

in terms of safety and radiation protection.

The general operating rules and the on-site emergency

plan for the facility have been revised. The facility’s waste

management study is also being revised. These revisions

bolster the licensee’s emergency response organisation

and integrate the latest changes in regulations.

ASN considers that the licenseemust continue its efforts

to embrace the regulations and be particularly attentive

to the time frames for performing its verifications and

periodic tests. ASN is attentive to the fact that the licensee

must prepare the first periodic safety review of the BNI

before November 2017 while maintaining sufficient

human resources for its two BNIs.

Meetings with the professionals

After the national seminar of 21st March2014, theMarseille

division pursued the discussions with the licensees at the

regional seminar held inMarseille on 6th October 2015,

in order to address the specific points relative to the BNIs

coming under the competence of the Marseille division

with the licensees concerned. This seminar provide a

MARSEILLE DIVISION

266

CHAPTER 08 :

REGIONAL OVERVIEW OF NUCLEAR SAFETY AND RADIATION PROTECTION

ASN report on the state of nuclear safety and radiation protection in France in 2015