Table of Contents Table of Contents
Previous Page  460 / 536 Next Page
Information
Show Menu
Previous Page 460 / 536 Next Page
Page Background

The aim of the strategy adopted in France is that:

the licensee prepares the decommissioning of its

installation from the design stage;

the licensee anticipates decommissioning before its

installationstopsoperatingandsendsthedecommissioning

authorisation application file before its installation is

shut down;

thedecommissioningoperationsarecarriedout“inasshort

a time as possible” after shutting down the installation, a

time which can vary from a few years to a few decades,

depending on the complexity of the installation.

1.2.2 Complete clean-out

The decommissioning and post-operational clean-out

operations for a nuclear installation must progressively

lead to elimination of the radioactive substances

resulting from the activation phenomena and/or of

any contamination deposits or migrations, in both the

structures of the installation premises and the ground

of the site.

The structure clean-out operations are defined on the basis

of the prior updating of the facility’s waste zoning plan

which identifies the areas in which the waste produced

is, or could be, contaminated or activated. As work

progresses (for example after cleaning the surfaces

of a room using appropriate products), the “possible

nuclear waste production areas” are downgraded to

“conventional waste areas”.

Pursuant to the provisions of Article 8.3.2 of the BNI Order,

“the final state reached on completion of decommissioning

must be such that it prevents the risks or inconveniences that

the site may represent for the interests mentioned in Article

L. 593-1 of the Environment Code, in viewmore particularly

of the projections for reuse of the site or buildings and the best

post-operational cleanout and decommissioning methods

available under economically acceptable conditions”.

In

this context, ASN recommends, in accordance with

its decommissioning policy developed in 2009, that

the licensees deploy clean-out and decommissioning

practices taking into account the best scientific and

technical knowledge available at the time and under

economically acceptable conditions, with the aim of

achieving a final status in which all the hazardous and

radioactive substances have been removed from the

BNI. This is the reference approach according to ASN.

Should it be difficult to apply this approach due to the

nature of the contamination, ASN considers that the

licensee must go as far as reasonably possible in the

clean-out process. Whatever the case, the licensee must

provide technical or economic elements proving that

the reference approach cannot be applied and that the

clean-out operations cannot be taken further under

acceptable economic conditions using the best technical

clean-out and decommissioning methods available.

In accordance with the general principles of radiation

protection, the dosimetric impact of the site on the

workers and public after decommissioning must be

as low as possible. ASN therefore considers that the

defining of a priori thresholds cannot be envisaged. More

specifically, achieving a threshold with an exposure level

leading to an annual dose of 300 µSv for the workers or

the public does not, in principle, constitute an acceptable

objective.

ASN is working on the updating of its technical guide

relative to structure clean-out operations (Guide No.14,

available on

www.asn.fr

) with a view to publication in

2016. It had been issued in 2010 in draft form pending

publication of the Order of 7th February 2012 and the

resolution on the study of management of the waste

produced in basic nuclear installations. The provisions of

this guide have already been implemented on numerous

installations with diverse characteristics, such as research

reactors, laboratories, fuel manufacturing plant, etc.

In 2015, ASN also produced a draft guide on the

management of polluted soil in nuclear installations.

It was made available to the stakeholders for consultation

in view of publication in the first quarter 2016.

1.3 Decommissioning regulatory

framework

From the moment a BNI is definitively shut down, it

must be decommissioned and therefore changes its

purpose with respect to that for which its creation

was authorised, as the creation authorisation decree

specifies, among other things, the operating conditions

of the installation. Furthermore, the decommissioning

operations imply a change in the risks presented by the

installation. Consequently, these operations cannot be

carried out within the framework set by the creation

authorisation decree. The decommissioning of a nuclear

installation is prescribed by a new decree issued after

consulting ASN. This decree sets out, among other things,

the main decommissioning steps, the decommissioning

end date and the final state to be attained.

In order to avoid fragmentation of the decommissioning

projects and improve their overall consistency, the

decommissioning file must explicitly describe all the

planned operations, from final shutdown to attainment

of the targeted final state and, for each step, describe the

nature and scale of the risks presented by the facility as

well as the envisaged means of managing them. This

file is subject to a public inquiry.

Given the fact that installation decommissioning

operations are often very long, the decommissioning

decree can stipulate that a number of steps will, when

the time comes, be subject to prior approval of ASN

on the basis of specific safety analysis files (previously

called “hold points”).

The diagram below illustrates the corresponding

regulatory procedure.

460

CHAPTER 15:

SAFE DECOMMISSIONING OF BASIC NUCLEAR INSTALLATIONS

ASN report on the state of nuclear safety and radiation protection in France in 2015