Table of Contents Table of Contents
Previous Page  466 / 536 Next Page
Information
Show Menu
Previous Page 466 / 536 Next Page
Page Background

ASN considers that the safety of decommissioning of

the Bugey reactor 1 is satisfactory on the whole, despite

occasional shortcomings in operating rigour.

ASN, which ensures labour inspectionon this installation,

has also noted deviations or near-accidents with regard

to occupational safety which must give rise to corrective

actions.

EDF’s decommissioning strategy for the gas-cooled

reactors (see point 2.1.1) will take into account the issue

of decommissioning the Bugey 1 reactor pressure vessel

in order to meet the deadline date for filling the Bugey 1

reactor with water is met (see point 2.1.1).

Chinon A1, A2 and A3 reactors

The former Chinon A1, A2 and A3 reactors were shut

down in 1973, 1985 and 1990 respectively.

Reactors A1 and A2 were partially decommissioned and

transformed into storage facilities for their own equipment

(ChinonA1D andChinonA2D). These operations were

authorised by the Decrees of 11th October 1982 and

7thFebruary 1991 respectively. ChinonA1D is currently

partiallydecommissionedandhas been set upas amuseum

since 1986. ChinonA2D is alsopartially decommissioned

and accommodates the Intra group (robots andmachines

for intervening on accident-strickennuclear installations).

The complete decommissioning of theChinonA3 reactor

wasauthorisedbyDecreeof18thMay2010.Thepreparatory

work for complete decommissioning was started by the

licensee in mid-2011. ASN gave its approval in 2012 for

the decommissioningworkon the exchangers (first step in

decommissioning of the facility) of theChinonA3 reactor.

ASNupdated the prescriptions regulating thewater intakes

and effluent discharges in 2015.

Decommissioning of the Chinon A3 heat exchangers

continued in 2015. Work has also started on Chinon A2.

The licensee’s monitoring of outside contractors on the

worksites remains a major issue in the decommissioning

of these installations.

The fire risk is well managed by the licensee, who has put

inplace a continuous improvement process to control this

risk. ASN has nevertheless noted a few deviations from

the corresponding new regulations.

ASN considers that the level of safety of the Chinon A

nuclear installations is satisfactory.

In 2016, ASN will also continue to monitor the various

actions carried out by the licensee concerning the

monitoring and implementation of a plan for managing

legacy hydrocarbon pollution of the soil.

In2016ASNwill state its positionon the decommissioning

schedule for the Chinon A reactors (see point 2.1.1) and

especially the decommissioning of ChinonA1DandA2D.

In the coming years, EDF should submit the conclusions

of the periodic safety reviews of the three reactors and the

decommissioning files for the Chinon A1D and Chinon

A2D reactors.

Saint-Laurent-des-Eaux A1 and A2 reactors

Complete decommissioning of the facility, which

comprises two reactors and for which final shutdown

was declared in 1994, was authorised by Decree of

18th May 2010. A file concerning the renewal of the

prescriptions regulating water intakes and effluent

discharges is currently being examined by ASN.

Since 2013, EDF has been carrying out expert appraisals

inside the vessel of reactors A2 and A1. The resulting data

served to produce a file substantiating the resistance of

the reactor structures and whose examination is nearing

completion.

The licensee has continued to progress with the

installation’s legacy waste and effluents treatment

work, despite unforeseen events that yet again affected

the worksites. A plan of action has been successfully

applied to improve operating rigour following several

deviations on one of the worksites in 2014 and 2015.

ASN has also observed satisfactory presence in the

field for the monitoring of outside contractors. The

licensee must therefore continue its actions in order to

be able to start the decommissioning operations, apart

from reactor pressure vessel A2, under satisfactory

conditions in 2016.

The fire risk is well managed by the licensee. ASN

has nevertheless noted a few deviations from the

corresponding new regulations.

ASN considers that on the whole the level of safety of

the nuclear installations of the former Saint-Laurent-

des-Eaux NPP is satisfactory.

EDF is going to carry out the periodic safety review of

the installations in the next few years.

2.1.5 Chooz A reactor

The reactor of the Ardennes NPP was the first pressurised

water reactor built in France. It was shut down in

1991. Its decommissioning foreshadowed the future

decommissioning of pressurised water reactors, the

technology of the French nuclear power reactors currently

in operation.

Within the context of partial decommissioning of the

reactor, the Decree of 19th March 1999 authorised

the modification of the existing facility to convert it

into a storage facility – called CNA-D – for its own

equipment left on site. Its complete decommissioning

was authorised by Decree of 27th September 2007.

466

CHAPTER 15:

SAFE DECOMMISSIONING OF BASIC NUCLEAR INSTALLATIONS

ASN report on the state of nuclear safety and radiation protection in France in 2015