Table of Contents Table of Contents
Previous Page  464 / 536 Next Page
Information
Show Menu
Previous Page 464 / 536 Next Page
Page Background

2. SITUATION OF NUCLEAR

INSTALLATIONS UNDERGOING

DECOMMISSIONING IN 2015

Somethirtyinstallationsarecurrentlybeingdecommissioned

in France (see map opposite).

2.1 EDF nuclear installations

2.1.1 The decommissioning strategy of EDF

The decommissioning strategy of EDF, the first version

of which was submitted to ASN at its request in 2001,

presents the decommissioning programme for the first-

generation Nuclear Power Plants (NPP) and the state

of reflections on the decommissioning strategy for the

fleet currently in operation.

As requested by ASN, EDF submitted an update of

the decommissioning strategy for its reactors in

October 2013. This file was examined by the advisory

committee of experts in 2015. ASN had asked EDF

beforehand to include a study of the alternative solutions

for graphite waste management in order to avoidmaking

decommissioning of the gas-cooled reactor vessels more

dependent on the commissioning of the Low-Level Long-

LivedWaste (LLW-LL) disposal facility. It nevertheless

notes that where decommissioning of gas-cooled reactors

is concerned, the question of the disposal route for

graphite waste can complicate correct implementation

of this immediate dismantling strategy.

The examinations of the safety of the installations, the

review of EDF’s decommissioning strategy and waste

management, and the Andra report on the technical

feasibility of a LLW-LL repository were communicated

in 2015.

On the basis of these new elements, the ASNCommission

will again hear EDF on the decommissioning strategy

for the gas-cooled reactors in March 2016. It will adopt

a position on the need to prescribe firstly the date for

opening the gas-cooled reactor vessels and secondly a

feasibility study for the creation of storage facilities for

managing the LLW-LL graphite waste.

2.1.2 Internal authorisations

The system of internal authorisations is governed by the

Decree of 2nd November 2007 (see chapter 3) and the

resolution of 11th July 2008. The aim of implementing

a system of internal authorisations in basic nuclear

installations is to consolidate the prime responsibility of

the operator with regard to nuclear safety and radiation

protection, one of the fundamental principles of the

safety of activities involving risks being that the person

or entity carrying them out is responsible for them. For

operations of minor importance it introduces flexibility

in the updating of the baseline safety requirements

of the facilities, whose state changes rapidly during

decommissioning. ASN, having authorised the EDF

system of internal authorisations relating essentially

to reactors undergoing decommissioning through a

resolution of 15th April 2014, conducted an inspection on

the subject in 2015 to check application of the resolution.

2.1.3 The Brennilis NPP

The Brennilis NPP on the Monts d’Arrée site, called

EL4-D, is an industrial prototype heavy water moderator

nuclear power reactor cooled with carbon dioxide

which was definitively shut down in 1985. The nuclear

operator since 2010 is EDF. Partial decommissioning

operations were carried out from 1997 to mid-2007

(plugging systems, dismantling certain heavy water

and carbon dioxide systems and electromechanical

components, demolition of non-nuclear buildings,

etc.). A Decree of 27th July 2011 authorised part of

the decommissioning operations with the exception

of decommissioning of the reactor unit. In 2015,

decommissioning of the installation continued under

this Decree (cleaning up of the soil situated around the

Effluent Treatment Station (STE), decommissioning

of the STE, decommissioning of the heat exchangers.

EDF must submit a complete decommissioning file

for this installation without delay.

During 2015, the licensee encountered several difficulties

in the decommissioning operations:

the heat exchanger decommissioning worksite was

interrupted on 23rd September 2015 when in the

clearing up and equipment removal phase, due to

a fire and triggering of the on-site emergency plan;

the clean-up and demolition worksite of the effluent

treatment stationwas interrupted several times, notably

by the incident involving the fall of a screeningmachine

which damaged the worksite containment.

ASN’s inspections further to these incidents revealed

deficiencies in the preparation of operations and in the

risk analyses, particularly with regard to consideration

of the fire risk.

ASN has asked EDF to review all the organisational

and human measures implemented to control the risks

associated with hot work on the decommissioning work

sites as soon as possible.

These difficulties led EDF to ask for an extension of

the deadline for performing the operations authorised

by the decree to that it can complete STE clean-out.

Clean-out of the STE and the subjacent soils should

continue in 2016.

464

CHAPTER 15:

SAFE DECOMMISSIONING OF BASIC NUCLEAR INSTALLATIONS

ASN report on the state of nuclear safety and radiation protection in France in 2015