Table of Contents Table of Contents
Previous Page  392 / 536 Next Page
Information
Show Menu
Previous Page 392 / 536 Next Page
Page Background

EDF has met all the regulatory deadlines and its

commitments.

Nevertheless, ASN has supplemented its demands with

a set of resolutions dated 21st January 2014 aiming to

clarify certaindesignprovisions of thehardened safety core.

ASN’s demands are part of a continuous process to improve

safety and aimtobe able to copewith situations far beyond

thosenormally considered for this type of installation. They

concernmeasures toprevent andmitigate the consequences

of an accident for all the installations on a site, beyond their

initial designconditions. They requirebothadditional fixed

resources andoff-sitemobile resources. In the international

context, these demands stand out through the scope and

scale of themeasures adopted in thewake of theFukushima

Daiichi accident.

Giventhenatureoftherequiredwork,thelicenseemustcarry

out studies for the design, construction and installation of

newequipment, which first require time and then require

a schedule to optimise their implementation on eachNPP.

Insofar as these major works are carried out on nuclear

sites which are in service, it is also necessary to ensure

that their implementation does not degrade the safety of

the power plants.

To take account of both the engineering constraints

involved in these major works and the need to introduce

the post-Fukushima improvements as soon as possible,

their implementation is planned in three phases:

Phase 1 (2012-2015)

Deployment of temporary ormobilemeasures to enhance

protection against the main situations of total loss of the

heat sink or electrical power supplies.

Attheendof2015,EDFhaddeployedtheplannedmeasures.

Phase 2 (2015-2020)

Deployment of definitive design andorganisationalmeans

that are robust to extreme hazards, to deal with the main

scenarios of total loss of the heat sink or electrical power

supplies beyond the baseline safety requirements in force.

The most important measures are:

installation of a large-capacity ultimate backup diesel-

generator set, requiring the construction of a dedicated

building to house it;

setting up of an ultimate water source;

creation of an ultimate water make-up system for each

reactor and each spent fuel pool;

reinforcement of the earthquake resistance of the

containment venting filter;

construction on each site of a local emergency centre

capable of withstanding extreme external hazards

(functionally independent in an emergency situation).

EDF had already started most of the studies needed to

deploy this equipment. However, discussions are still in

progress concerning the schedule todeploy thesemeasures

on each of the EDF reactors andASNwill issue a position

statement on this subject in 2016.

Phase 3 (as of 2019)

This phase will supplement phase 2, in particular to take

account of other potential accident scenarios. The most

important measures are:

removal of the residual power by the steam generators

bymeans of an independent ultimate backup feedwater

system supplied by the ultimate heat sink;

addition of a newmakeuppump to the primary system;

completion of the fixed connection systems for the SG

backup feedwater supply, the PTR cooling water tank

and the spent fuel pit;

installation of an ultimate instrumentation & control

systemand thedefinitive instrumentationof the “hardened

safety core”;

installation of a reactor containment ultimate cooling

systemthat does not require opening of the containment

venting-filtration systemin the event of a severe accident;

implementation of a solution for flooding the reactor pit

to prevent coriummelt-through of the basemat.

EDF still has to conduct feasibility studies on these latter

two points. Discussions on the schedule for deployment

of the provisions of phase 3 for each of the EDF reactors

are in progress and ASN will issue a position statement

on this subject in 2016.

3.2 Examination of NPP operating

life extensions

The licensee of a nuclear facilitymust conduct a periodic

safety reviewof its facility every ten years (see point 2.9.4).

The reactors of the 900 MWe plant series

The periodic safety review associated

with the third ten-yearly outage inspections

In July 2009, ASN issued a position statement on

the generic aspects of an operating life extension for

the 900 MWe reactors beyond 30 years. ASN has not

identified any generic element that would compromise

EDF’s ability tomanage the safety of the 900 MWe reactors

until the next periodic safety review. ASN considers

that the new baseline safety requirements presented

in the generic safety report for the 900 MWe reactors

and the modifications to the installation envisaged by

EDF are such as to maintain and improve the overall

level of safety of these reactors.

As this generic assessment does not take account of any

individual specific features, ASN gives an opinion on

the ability of each reactor to continue to function, more

specifically based on the results of inspections performed

during the reactor conformity check during the third

392

CHAPTER 12:

EDF NUCLEAR POWER PLANTS (NPPs)

ASN report on the state of nuclear safety and radiation protection in France in 2015