Table of Contents Table of Contents
Previous Page  397 / 536 Next Page
Information
Show Menu
Previous Page 397 / 536 Next Page
Page Background

and to ensure the cleanness of the working areas and

the assembled equipment.

ASN and the approved organisation review the technical

documentation concerning assembly operations and the

monitoring of the assembly or manufacture of nuclear

pressure equipment carried out on the site. ASN and the

approved organisations require that Areva NP analyse

the feedback from one assembly sequence before

initiating the next one. This was in particular the case

following the discovery in late 2014 and in 2015 of

defects in several primary systemwelds. These defects

occurred during connection of the steam generators

to the primary system and during welding of a section

of the Pressuriser Expansion Line (LEP). In the first

case, investigations are still in progress to look at the

origin of the welding defects detected and the corrective

measures required. In the second case, the weld affected

was repaired and welding of the other LEP sections

continued. In 2015, ASN carried out three inspections

of Areva NP on the assembly of the NSSS and four

inspections of the inspection organisations or bodies

approved by ASN to monitor these activities. These

inspection organisations and bodies themselves carried

out several hundred inspections in 2015.

The NSSS assembly operations will be gradually

expanded, after ASN checks that the experience acquired

during the activities has been taken into account.

3.4 The other notable findings

of 2015

3.4.1 Notable findings relating to oversight

of pressure equipment

Replacement of steam generators intended

for Le Blayais reactor 3

At the end of 2014, after examining the design and the

manufacture of the new steam generators intended for

reactor 3 in the Le Blayais NPP, ASN found Areva NP

had not provided all the required safety justifications.

On 24th November 2014, ASN therefore asked Areva NP

and EDF to provide additional safety justifications.

These were the pre-requisites for installation and then

commissioning of these steam generators.

Since then, Areva has provided the additional

information enabling these preconditions to be lifted.

On 24th July 2015, ASN therefore issued the conformity

assessment reports for the three replacement steam

generators for Le Blayais reactor 3, enabling them to

be started up by EDF.

3.4.2 Notable findings relating to labour

inspectorate duties

Oversight of occupational health and safety

With regard to occupational health and safety, the ASN

inspectionsmore specifically covered the following topics

in 2015:

monitoring of construction site activities, with particular

attention being paid to lifting work and risks linked

to work being performed by several contractors

simultaneously and to work at height;

the use of Carcinogenic, Mutagenic or Reprotoxic

chemical products, asbestos, or welding activities;

fire protection measures as part of an integrated and

coordinated approach to safety and Labour Code

requirements;

operating experience feedback from the viewpoint of

occupational safety during steamgenerator replacement

operations;

risk assessment and prevention during preparations

for the operations requiring personnel entry inside

the steam generators or reactor buildings at power;

mandatory checks on polar cranes in reactor buildings

and the heavy-lift cranes in the fuel buildings.

Occupational accident inquiries, which are always held

in the event of a severe accident, were rare in 2015, and

no fatal accident occurred.

Monitoring working hours

In 2015, the ASN labour inspectors continued

their checks on compliance with the regulations on

working hours and on daily and weekly rest periods,

mainly during the reactor outages. They once again

observed breaches of maximum working hours and

rest periods, for certain populations of technicians and

managers required to work intensively during reactor

outage periods. Contacts were made with the public

prosecutor’s offices concerned in order to follow up

the procedures initiated.

International subcontracting and provision

of services

ASN closelymonitors the criminal proceedings instigated

in previous years, more specifically through regular

contacts with the public prosecutor’s offices. The labour

inspectors also took part in several inspections jointly

with the nuclear safety inspectors, to look at the quality

of the work done by the contractors. Inspections were

carried out on the conditions for secondment of staff

from foreign contractors.

Criminal proceedings

The ASN labour inspectorate sent the various Public

Prosecutor’s departments concerned four formal notices

served on the NPPs in 2015.

397

CHAPTER 12:

EDF NUCLEAR POWER PLANTS (NPPs)

ASN report on the state of nuclear safety and radiation protection in France in 2015