Table of Contents Table of Contents
Previous Page  394 / 536 Next Page
Information
Show Menu
Previous Page 394 / 536 Next Page
Page Background

Paluel reactor 2 is the first 1,300 MWe reactor to undergo

a third ten-yearly outage inspection, which started in

2015.

The reactors of the 1,450MWe plant series

The periodic safety review associated

with the first ten-yearly outage inspections

The generic studies and modifications associated with

the first periodic safety reviews of the 1,450 MWe

reactors were the subject of an ASN position statement

in 2012, which in particular requested additional work

by EDF to demonstrate the adequacy either of the

studies conducted, or of the modifications made to

the installations during their first ten-yearly outage

inspection, in order to comply in full with the objectives

set in the periodic safety review.

The first ten-yearly outage inspections took place

between 2009 and  2012.

EDF’s answers and the periodic safety review conclusions

reports for the four 1,450 MWe reactors are currently

being assessed and ASN intends to issue its position

statement on their continued operation to the Minister

in charge of Nuclear Safety in 2016.

The periodic safety review associated

with the second ten-yearly outage inspections

In 2011, EDF transmitted its orientation proposals

for the generic studies programme for the periodic

safety review associated with the second ten-yearly

outage inspections of the 1,450 MWe reactors. After

consulting the GPR in 2012, EDF supplemented its

generic studies programme with a number of measures

and clarified some of its proposals. In February 2015,

ASN ruled on the orientations of the periodic safety

review associated with the second ten-yearly outage

inspections of the 1,450 MWe reactors. ASN more

specifically considers that the safety objectives to be

considered for the VD2 N4 safety review must be

defined in the light of the objectives applicable to the

new reactors and asked EDF to study the measures

liable to comply with this requirement as rapidly as

possible, so that they can be implemented as of the

second ten-yearly outage inspections on the reactors

of the N4 plant series.

The second ten-yearly outage inspections for the

1,450 MWe plant series reactors are scheduled to

start in 2018 with the Chooz B2 reactor and will run

until 2022.

3.3 Monitoring of the EPR

Flamanville 3 reactor

Oversight of the Flamanville 3 engineering activities

In 2015, ASN carried out three inspections in the EDF

engineering departments responsible for the detailed

design studies for Flamanville 3, for drafting the

partial commissioning authorisation application files

for Flamanville 3, for defining the start-up tests to be

performed or for monitoring manufacturing operations

at the suppliers.

Examination of the commissioning

authorisation application and

the partial commissioning authorisation

application for Flamanville 3

On 19th March 2015, ASN received the commissioning

authorisation application for Flamanville 3. With IRSN,

its technical support organisation, ASN carried out a

preliminary review of this application to check that it

contains all the documents required by the regulations

and the necessary information to allow a full technical

examination. Following this preliminary examination,

ASN confirmed that all the documents required by the

regulations were indeed present, but it considered that

additional information was needed to enable ASN to

rule on a possible commissioning authorisation for

Flamanville 3. The additional information requested

in particular concerns the conformity of the as-built

installation with the file submitted, the dimensioning

of the systems and the accident studies.

ASN did however begin a technical examination of

the file on those subjects for which only very little

data was still missing. Some subjects, such as the

substantiation of the critical heat flux correlation, gave

rise to requests from ASN. Two GPR meetings were

thus devoted to Flamanville 3 in 2015: one covering

technical, organisational and human resources, defined

for reactor normal operating conditions and accident

operating conditions; the other covering the management

of severe accidents, their radiological consequences

and the level 2 probabilistic safety assessments. ASN

will shortly be issuing its requests resulting from these

meetings.

Furthermore, on 19th March 2015, ASN received

the partial commissioning authorisation application

for Flamanville 3, needed to admit fuel within the

perimeter of the facility and carry out certain tests.

ASN carried out a preliminary examination of this file,

which concluded that a certain amount of additional

information was required, more specifically to assess

the risks and detrimental effects which could result

from tests using radioactive tracer gases to verify the

correct operation of certain effluent treatment systems.

394

CHAPTER 12:

EDF NUCLEAR POWER PLANTS (NPPs)

ASN report on the state of nuclear safety and radiation protection in France in 2015