Table of Contents Table of Contents
Previous Page  473 / 536 Next Page
Information
Show Menu
Previous Page 473 / 536 Next Page
Page Background

BNI 80 comprises five facilities:

HAO North, fuel unloading and storage site;

HAO South, in which the shearing and dissolution

operations were carried out;

the filtrationbuilding,whichaccommodates the filtration

system for the pool of the HAO South facility;

The HAO silo, in which are stored the hulls and end-

pieces in bulk, fines coming essentially from shearing,

resins and technological waste resulting fromoperation

of the HAO facility from 1976 to 1997;

the SOC (Organised Storage of Hulls) comprising three

pools inwhich the drums containing the hulls and end-

pieces are stored.

Thedecommissioningof theHAOwas authorisedbyDecree

of 31st July 2009. The first stage in the work which aims

at carrying out the majority of the HAO South facility

decommissioningoperations is inprogress. TheHAONorth

facility, which is still inoperation, will be decommissioned

in a second phase.

TheWasteRetrieval andPackaging (RCD) project currently

under way in the HAO silo and the SOC represents the

first holdpoint in the decommissioning of the installation.

The civil engineeringworks concerning the construction

of the waste retrieval and packaging unit authorised by

resolution of 10th June 2014 continued in 2015. The

licensee alsoput inplace a seal between theR1unit situated

in BNI 117 and the retrieval unit.

ASNismoreover vigilantwith regard to the implementation

times for these operations,whichmust be completedbefore

31st December 2022.

Furthermore, BNI 80 formed the subject of aperiodic safety

review, the examinationof whichwill be finalised in2016.

BNIs 33 and 38

InOctober 2008, ArevaNCsubmitted three final shutdown

anddecommissioning authorisationapplications for BNI 33

(UP2-400), BNI 38 (STE2 and AT1 facility) and BNI 47

(ELAN IIB).

On completion of the technical examination of the files

submitted in 2008, ASN considered that the measures

defined byArevaNC for the decommissioning of BNIs 33

and38 showednothingunacceptablewith regard to safety,

radiation protection or waste and effluent management.

Nevertheless, this examination did reveal the necessity

for the licensee to provide a large number of additional

studies. Consequently, only those operations forwhich the

information in the safety cases was considered sufficient

could be authorised for BNIs 33 and 38.

The threedecrees authorising the start of the final shutdown

and decommissioning operations for the three BNIs date

from 8th November 2013. The decrees concerning

BNIs 33 and 38 only authorise partial decommissioning,

whereas thedecree concerningBNI 47 authorises complete

decommissioning of the installation.

The decrees for BNIs 33 and 38 required the licensee to

submit new files before 30th June 2015. The licensee

therefore submitted new complete decommissioning

application files for BNIs 33 and 38 in July 2015. It also

submitted the periodic safety review files for BNIs 33, 38

and 47. Concomitant examination of the periodic safety

review files and the decommissioning files will allow

the compatibility of the ageing control measures with

the decommissioning strategy envisaged by the licensee

–particularly theprojecteddurationof thedecommissioning

project as a whole – to be checked.

The operations carried out in 2015 essentially concern

the retrieval of the waste from the dissolvers in the High

Activity /DissolutionExtraction (HA/DE) facility, continued

removal of the glove boxes from the Intermediate-level

PlutoniumFacility (MAPu), oxalic acid rinsing of theHigh-

Level Fission Products (HAPF) facility and conducting

various investigations and radiological mappings.

The legacy waste of La Hague

The legacy waste to be retrieved and packaged on the

La Hague site comes from the reprocessing of spent fuel from

the gas-cooled reactors and the first spent fuels from the light

water reactors in the UP2-400 industrial plant between 1966

and 2004. This waste, which is primarily Intermediate Level

Long-Lived Waste (ILW-LL), essentially comprises graphite

sleeves, hulls and end-pieces, insoluble fines, saturated resins,

magnesium waste, waste contaminated with uranium and

plutonium, active effluent treatment sludge, solvents and

solutions of uranium-molybdenum fission products (PF UMo).

Today this waste is stored in several old-generation facilities

displaying varying levels of safety, but which are unsatisfactory

on account of their layout (buried or semi-buried), their design

(containment barriers), their earthquake design basis and

the nature of the waste stored in them. The waste must thus

be retrieved from the storage facilities using the retrieval

equipment planned for when these facilities were designed,

or using equipment to be designed if these facilities do not

have any. Once retrieved, the waste must be packaged with a

view to final disposal. Retrieval of this waste will also clear the

facilities of their waste allowing them to be decommissioned

and cleaned out in the context of the UP2-400 industrial plant

(BNI 33, 38, 47 and 80) decommissioning operations.

ASN resolution of 9th December 2014 governs the retrieval of

this waste.

UNDERSTAND

473

CHAPTER 15:

SAFE DECOMMISSIONING OF BASIC NUCLEAR INSTALLATIONS

ASN report on the state of nuclear safety and radiation protection in France in 2015