Table of Contents Table of Contents
Previous Page  475 / 536 Next Page
Information
Show Menu
Previous Page 475 / 536 Next Page
Page Background

proceed. These clarification requests concern general

aspects in the decommissioning strategy adopted by

Eurodif Production, more particularly in themanagement

of radioactive waste and the description of the initial

and final states of the installation.

The last rinsing operations were completed in

October 2015 under what ASN considers to be satisfactory

conditions, apart from the end-of-soaking criteria actually

used, which differ from those specified in the safety

baseline requirements, whichmust be taken into account

if necessary in the decommissioning input data. Since

these operations were completed there is no chlorine

trifluoride (ClF

3

) in the facility.

Due to technical difficulties, particularly concerning the

qualification of new equipment items, the operations to

pressurise the cascade with air did not start until 2015

and will continue until mid-2016.

ASNmoreover authorised the operations to pressurise

the DRP unit with air and the final shutdown of the

units of annex U for treating substances extracted

from the diffusion cascade. It is currently examining

the rinsing authorisation application for the annex U

systems. After completion of all these operations, which

will have eliminated the majority of the source term,

the plant will be in a surveillance phase until the first

decommissioning operations are started.

ASN will ensure that in 2016 the last operations of the

Prisme project are carried out in strict compliance with

the authorisations it has delivered.

2.3.4 SICN plant in Veurey-Voroize

The former nuclear fuel fabrication plant of Veurey-

Voroize, operated by the

Société Industrielle de Combustible

Nucléaire

(SICN - Areva Group) consists of two nuclear

facilities, BNIs 65 and 90. Fuel fabrication activities were

definitively stopped in the early 2000’s. The Decrees

authorising the decommissioning operations date from

15th February 2006. The decommissioning work has

now been completed.

The site nevertheless displays residual contamination

of the soil and groundwater, the impact of which is

acceptable for its envisaged future use (industrial). ASN

has therefore asked the licensee to submit, as a prerequisite

to delicensing, an application for the implementation of

active institutional controls designed to restrict the use of

the soil and groundwater and to guarantee that the land

usage remains compatible with the state of the site. SICN

submitted this file to the Isère

département

Prefecture

in March 2014, and the delicensing application file for

the two BNIs to ASN. Delicensing will not be able to be

declared until these active institutional controls have

been effectively put in place by the Prefect of the Isère

département

, at the end of the examination procedure

which includes a public inquiry.

2.4 Other installations

The Electromagnetic Radiation Laboratory (LURE)

The LURE, situated in the heart of the Orsay campus,

was an installation producing synchrotron radiation

(high-power X-rays) for a wide variety of research

applications. It comprised six particle accelerators.

CNRS (French National Centre for Scientific Research),

the LURE licensee, was authorised to proceed with

final shutdown and decommissioning by Decree on

14th April 2009.

The decommissioning operations were completed in

2010. As provided for by the above-mentioned decree,

the CLIO and PHIL accelerators are kept in activity;

moreover, two areas with residual activity linked to the

presence of the electron converters subsist. The cleaning

out of these areas required the destruction of part of the

civil engineering calling into question the mechanical

strength of the building as a whole, therefore during

the examination it had been planned to put biological

protections in place.

The licensee submitted its decommissioning file in

spring 2011. Delicensing of the LURE waste zoning,

except for the area with residual activity, was declared

in 2012. The LURE BNI 106 was delicensed by

resolution of 27th October 2015. The Prefect of the

Essonne

département

issued an order introducing active

institutional controls on 1st October 2015.

Performance of intensive rinsing operations - Monitoring of Eurodif venting (Prisme). Eurodif plant

decommissioning worksite on Areva NC’s Tricastin site.

475

CHAPTER 15:

SAFE DECOMMISSIONING OF BASIC NUCLEAR INSTALLATIONS

ASN report on the state of nuclear safety and radiation protection in France in 2015