Table of Contents Table of Contents
Previous Page  471 / 536 Next Page
Information
Show Menu
Previous Page 471 / 536 Next Page
Page Background

BNIs but whichhave not been completely dismantleddue

to the absence of a disposal route for low-level long-lived

waste. Their delicensing in the 1980’s from BNI status to

ICPE status, in compliance with the regulations of that

time, would not be possible today.

High-Activity Laboratory (LHA)

The LHA comprises three buildings housing several

laboratories which were intended for research into or

the production of various radionuclides. On completion

of the decommissioning and clean-out work authorised

byDecree of 18th September 2008, only two laboratories

currently inoperation shouldultimately remainunder the

ICPE system. These two laboratories are the laboratory for

the chemical and radiological characterisation of effluents

and waste, and the packaging and storage facility for the

recovery of sources that are surplus to requirements.

The decommissioning of the cells, tanks and liners present

in the intercell yards of the BNI continued in2014. After a

preparatoryphase,decommissioningoftheTOTEMshielded

chain, whichwas stopped in2012, started again. The first

operations to clean out the civil engineering structures of

the decommissioned cells started in 2015.

ASN considers that the safety of BNI 49 undergoing

decommissioning remains satisfactory and notes that the

decommissioning operations are proceeding according

to the schedules. The commitments made further to the

inspections and significant events arewellmet on thewhole.

Nevertheless, the inspections carriedout in2015 revealed

shortcomings in the management of decommissioning

waste movements and storage areas, which led to the

notification of several significant events.

More generally, themajorityof event notificationsweremade

further to an ASN inspection, which tends to show that

the deviation detection and analysis process, particularly

concerning the results of inspections and periodic tests,

is not robust.

The cell clean-out operations will continue in 2016.

The level of subcontracting is particularly high on this

BNI. Control of the operations performed by outside

contractors is an important issue. In this context and

in view of observed deviations, ASN considers that

CEA must not simply question the organisation and

resources of these contractors, but also question its

own organisation and means deployed to control the

services of its subcontractors.

Ulysse reactor

Ulyssewas the first French university reactor. The facility

has beendefinitively shut down since February 2007. The

facility has had no fuel since 2008. The final shutdown

and decommissioning authorisation decree for the BNI

was published on 18th August 2014 and provides for a

five-year decommissioning period.

BNI 18 is an installation whose decommissioning has

just started and for which the risks with regard to safety

are limited.

The installation is ageing and modifications have been

introduced toallowits futuredecommissioning (appropriate

ventilation, specific electrical switchboard, procurement

of gantry, etc.). Unnecessary items have been removed

(batteries, documentation, etc.). In2015, CEAprepared the

installation for decommissioning by arranging the external

areas, receiving the ventilation unit and dismantling and

removing the control room.

The decommissioning operations will start in 2016. The

level of subcontracting will be particularly high on this

BNI. ASN will be attentive to the control of operations

performed by outside contractors.

2.2.5 The Marcoule centre installations

undergoing decommissioning

The Phénix reactor

The Phénix reactor, built andoperatedbyCEA, is a sodium-

cooled fast neutron reactor demonstrator. Itwas definitively

shut down in 2009. The decommissioning authorisation

application filewas submitted inDecember 2011.Within

the frameworkof the examinationof this decommissioning

application, CEA also anticipated the plant’s next periodic

safety reviewby submitting its file toASNat the endof 2012.

The AdvisoryCommittee of Experts for Laboratories and

Plants (GPU) met on 12th November 2014 and issued

a favourable opinion on the continued operation of the

installation with a view to its decommissioning, on the

performance of the final shutdown anddecommissioning

operations, andon the treatment of the sodiumandobjects

containing sodium from the Phénix power plant. ASN

sent its conclusions on the technical examination and

the consultations to the Minister responsible for Nuclear

Safety and issued its opinion on 22nd December 2015.

Preparatory operations for the decommissioning of the

Phénix power plant continued in 2015 and essentially

involved unloading the fuel storage tank and the vessel,

preparing carbonationof the residual films of sodiumfrom

the secondary systems, and fitting out the future premises

or units necessary for the decommissioningwork (NOAH

worksite, etc.). CEAnevertheless encountereddifficulties

during unloading of the fuel storage tanks and the vessel

due to problems linked to the ageing of certain items

of equipment in the shielded cells for treating irradiated

assemblies and experimental objects.

The inspections in 2015 focused on occupational

radiation protection, waste management, monitoring

outside contractors, operational control of the facilities

and compliance with operating documents. Moreover,

shortcomings in themonitoringof outside contractorswere

471

CHAPTER 15:

SAFE DECOMMISSIONING OF BASIC NUCLEAR INSTALLATIONS

ASN report on the state of nuclear safety and radiation protection in France in 2015