Table of Contents Table of Contents
Previous Page  470 / 536 Next Page
Information
Show Menu
Previous Page 470 / 536 Next Page
Page Background

contained. The reactor pool has been emptied, partially

cleaned out anddecommissioned. In addition, 23 tonnes

of sodium are stored and must be removed to the CEA

Marcoule centre for treatment.

The CEA transmitted its complete decommissioning

authorisationapplication toASNinDecember 2014and the

periodic safety review file for the installation inMay 2015.

In July 2015, ASN informed the Minister responsible for

Nuclear Safety, who had referred this file to ASN, that

further information was necessary in order to continue

the examination.

TheworkcurrentlybeingperformedbyCEAchiefly involves

renovation, clean-out and decommissioning operations

limited to specific equipment items, along with waste

removal operations. ASN considers that the standard

operating operations are carried out regularly, that the

premises arewell kept and that substantial workhadbeen

carried out tomake the applicable documents consistent

with the general operating rules. The measures taken by

CEA to ensure removal of the sodium-containing waste

still present in the installation by 2018 are also closely

monitored by ASN.

Thepurpose of theLDAC, locatedwithin theRapsodieBNI,

was toperforminspections and examinations on irradiated

fuels from the fast-neutron reactors. This laboratory has

been shut down since 1997 and partially cleaned out. Its

decommissioning is included in the decommissioning

project for the entire BNI.

Two successive significant events that occurred in the

radiochemistry laboratory early in the year highlighted

the singular situation of this installation classified on

environmental protectiongroundswithin theBNI. TheBNI

licensee reacted appropriately bymaking improvements in

the organisation of the interfaces with this laboratory and

through safety awareness-raising actionswith its personnel.

Enriched Uranium Processing Facilities (ATUEs)

Until1995,theATUEsconverteduraniumhexafluoridefrom

the enrichment plants into sinterable oxide, and ensured

the chemical reprocessing of waste fromthemanufacture

of fuel elements. The installationwas also equippedwith

a low level organic liquid incinerator. Production in the

facilities ended in July 1995 and the incinerator was shut

down at the end of 1997.

The installation’s final shutdown and decommissioning

authorisation Decree of 8th February 2006 prescribed

work completion in 2011. After having observed that the

decommissioningoperationswerestoppedandthatCEAhad

not followed up its request to submit a newauthorisation

application file inorder to complete the decommissioning,

ASN served CEA with a compliance notice on 6th June

2013. InFebruary 2014CEA submitted a newapplication

for authorisation to complete the decommissioning and

clean-out operations. Considering that this filemeets the

conditions set in the compliance notice resolution, ASN

suspendedthenoticeresolutionbyaresolutionon29thApril

2014. However, it turnedout that further informationwas

required, whichASN indicated to theMinister responsible

for Nuclear Safety who had referred this file to ASN. The

additional informationwas provided inDecember 2015.

The Plutonium Technology Facility (ATPu) and the

Chemical Purification Laboratory (LPC)

TheATPuproducedplutonium-based fuel elements initially

intended for fast neutron or experimental reactors and

then, as of the 1990s, for pressurisedwater reactors using

MOX fuel. The LPC’s activitieswere associatedwith those

of the ATPu: physical-chemical checks andmetallurgical

examinations, treatment of effluents and contaminated

waste. The two facilities were shut down in 2003.

CEA is the nuclear licensee for these facilities. Areva NC

has been the industrial operator responsible for operation

of the facilities since 1994 and is also responsible for their

decommissioning until CEA takes over this latter activity

completely, which is planned for the second half of 2016.

Decommissioning of the two facilities, authorised by the

Decrees of 6thMarch2009 andgovernedby the resolutions

of 26th October 2010, continued in 2015 with a large

volume of operations, resulting in a significant reduction in

the source term. For some of these operations the licensee

mademodificationdeclarations, examinedbyASN, suchas

the retrieval of bitumen fromthe annular tanks of the LPC.

With regard to the cryogenic treatment unit, the

decommissioningoperations authorisedbyASNresolution

of 20th October 2011 are in progress.

ASNhas kept close trackof implementationof themeasures

takenbyCEA further to the compliancenotice resolutionof

19thFebruary2013concerningmonitoringofAreva NCand

management of the skills associatedwithdecommissioning

safety, and the organisation put in place by the operator

appears to be effective on the whole.

In2016ASNwill remain attentive to the situation of these

two BNIswith regard to social, organisational andhuman

factors, and will see to the long-term continuation of the

progress registeredso that the resumingof decommissioning

activitiesbyCEAafterthedepartureoftheindustrialoperator

takes place under suitably safe conditions.

2.2.4 The Saclay centre installations

undergoing decommissioning

The decommissioning operations carried out on the

site concern two BNIs in final shutdown state and three

BNIs in operation but with sections that have stopped

their activity and on which preparatory operations for

decommissioning are being carriedout. They also concern

two ICPEs (Installations Classified on Environmental

Protection grounds), EL2 andEL3, whichwere previously

470

CHAPTER 15:

SAFE DECOMMISSIONING OF BASIC NUCLEAR INSTALLATIONS

ASN report on the state of nuclear safety and radiation protection in France in 2015