Table of Contents Table of Contents
Previous Page  467 / 536 Next Page
Information
Show Menu
Previous Page 467 / 536 Next Page
Page Background

After decommissioning the steam generators and the

primary system, ASN, through its resolution of 3rdMarch

2014, authorised decommissioning of the reactor vessel

which is planned to start in 2016.

The preparatory work for decommissioning the Chooz A

reactor vessel started in 2015. The reactor cavity gates

were dismantled and the pressuriser, dismantled in

2013, was removed.

With regard to the environment and nuclear safety,

ASN considers that the decommissioning operations

are being carried out satisfactorily.

Regarding radiation protection, in 2015 ASNobserved the

progress made by EDF under the action plan implemented

in 2014. ASN considers that EDF must maintain its

training and awareness-raising efforts for its outside

contractors in this area.

Several incidents occurred during operations on

electrical distribution panels in 2014 and 2015 due

to insufficient preparation of the activities concerned

and to concomitance of activities.

EDF must have completed the periodic safety review

of Chooz A in 2017. ASN examined the orientations

of this safety review in 2015.

2.1.6 The Superphénix reactor

and the Fuel Evacuation Facility (APEC)

The Superphénix fast neutron reactor, a sodium-cooled

industrial prototype, is located at Creys-Malville. It

was definitively shut down in 1997. This installation is

associated with another BNI, the Fuel Evacuation Facility

(APEC), which consists primarily of a storage pool in

which the spent fuel removed from the Superphénix

reactor vessel is stored, and storage for packages of

soda concrete from the Sodium Treatment Installation

(TNA).

ASN considers that the safety of the Superphénix reactor

decommissioning operations and of APEC operation is

satisfactorily ensured. The progress ASN observed in

2014 with regard to operating rigour and monitoring

the performance of maintenance operations and periodic

tests was maintained in 2015.

In addition, following the detection of anomalies in 2014,

the licensee has listed the retention structures on the

site and defined corresponding inspection programmes.

Nevertheless, in 2015 ASN asked EDF to rapidly set up

an organisational structure enabling it to remove and

treat, as rapidly as possible, the hazardous substances

that could accumulate in the retention structures.

Lastly, ASN has verified that the organisation and

provisions with regard to occupational radiation

protection and the transport of radioactive substances

complied with the regulations.

Examination of the file transmitted for the authorisation

to treat the residual sodium from the reactor vessel and its

filling withwater revealed no blocking points. Preparation

and performance of these operations represent the main

risk activities for the coming year. The periodic safety

review files for the Superphénix reactor and the APEC

were submitted in 2016. ASNmade a statement in 2014

on the orientations of the then forthcoming periodic

safety reviews and will start the technical examination

of the files received.

The implications of decommissioning

the PWR vessel

The Chooz A reactor is a Pressurised Water Reactor (PWR)

like EDF’s 58 reactors in operation. It is therefore the first reactor

using this technology to be decommissioned in France by EDF

and the first shut down reactor to have its vessel dismantled.

Decree 2007-1395 of 27th September 2007 authorising

decommissioning of the Chooz A reactor set four hold points:

dismantling of the primary system, dismantling of the reactor

vessel, start of stages 2 (surveillance phase) and 3 (demolition

and redevelopment of the site), considering that the change

of stage operations require a specific examination.

ASN thus authorised dismantling of the reactor vessel in 2014.

The main challenges of dismantling the reactor vessel are:

1 - Worker radiation protection is a major issue. This is because

the reactor vessel, the metal of which has been activated,

cannot be decontaminated beforehand (unlike the already

dismantled steam generators) to reduce the dose rate.

EDF has therefore planned to carry out the operations

to remove the elements from the vessel and cut up

of the vessel under water in the reactor cavity, using

remotely operated means.

2 - There is a risk associated with the handling of large

components (the vessel weighs about 200 tonnes).

3 - New facilities must be built to treat and package the waste.

4 - Waste management represents a major challenge since

the activated waste, once characterised and packaged, must

be transferred to ICEDA (activated waste packaging and

interim storage installation). This facility will therefore have

to be put into service within a time frame compatible with

the progress of vessel dismantling.

To cope with these challenges, EDF has the benefit of

international experience feedback from reactors of identical

technology on which this same procedure has been used,

particularly the Zorita NPP in Spain.

UNDERSTAND

467

CHAPTER 15:

SAFE DECOMMISSIONING OF BASIC NUCLEAR INSTALLATIONS

ASN report on the state of nuclear safety and radiation protection in France in 2015