Table of Contents Table of Contents
Previous Page  500 / 536 Next Page
Information
Show Menu
Previous Page 500 / 536 Next Page
Page Background

ASN issued a favourable opinion (ASNopinion 2015-AV-

0228 of 26th March 2015) on the draft creation Decree

for the Ecrin BNI. The Ecrin facility was authorised by

Decree of 20th July 2015 for the storage of radioactive

waste for a period of thirty years with a volume of waste

not exceeding 400,000 m

3

and total radiological activity

of less than 120 terabecquerels (TBq).

The Ecrin facility commissioning authorisation application

was submitted by Areva NC on 15th October 2015 and

will be examined in 2016.

1.5.3 EDF waste management

EDF waste management strategy

The waste produced by EDF nuclear power plants is

activated waste (from reactor cores) and waste resulting

from their operation and maintenance. To this can be

added some legacywaste andwaste resulting fromongoing

decommissioningoperations. EDF is also the owner, for the

share attributed to it, of HL and IL-LLwaste resulting from

spent fuel reprocessing in the Areva NC La Hague plant.

Activated waste

This waste notably comprises control rod assemblies

and poison rod assemblies used for reactor operation.

This is IL-LL waste that is produced in small quantities.

This waste is currently stored in the NPP pools pending

transfer to the ICEDA facility.

Operating and maintenance waste

Some of the waste is processed by the Centraco facility in

Marcoule in order to reduce the volume of ultimate waste.

The other types of operational and maintenance waste

are packaged on the production site then shipped to the

CSA or CIRES repositories for disposal (see points 1.3.1

and 1.3.2). This waste contains beta and gamma emitters,

and few or no alpha emitters.

At the end of 2013, EDF submitted a file presenting its

waste management strategy. This file was examined by

the competent Advisory Committees of Experts (GPE)

in 2015. ASN will issue a position statement on this

file in 2016.

The issues and implications

The main issues related to the EDF waste management

strategy concern:

the management of legacy waste. This primarily

concerns structural waste (graphite sleeves) from the

graphite-moderated gas-cooled reactor fuels. This

waste could be disposed of in a repository for LLW-LL

(see point 1.3.4). It is stored primarily in semi-buried

silos at Saint-Laurent-des-Eaux. Graphite waste is

also present in the form of stacks in the gas-cooled

reactors currently being decommissioned.

changes linked to the fuel cycle. EDF’s fuel use policy

(see chapter 12) has consequences for the fuel cycle

installations (see chapter 13) and for the quantity

and nature of the waste produced. This subject was

examined by the Advisory Committee of Experts for

Nuclear Reactors (GPR) and the Advisory Committee

of Experts for Laboratories and Plants (GPU) on

30th June 2010. Following this examination, in its

letter of 5thMay 2011, ASN asked EDF to implement a

more rigorous policy for managing its storage capacity

for substances before their disposal, treatment or

reprocessing (see chapter 13). More specifically

with regard to waste, EDF must for example ensure

that the available packaging containers can meet the

disposal needs.

Facilities operated by EDF to support this strategy

ICEDA (BNI 173)

The purpose of the ICEDA facility, authorised by Decree

on 23rd April 2010, is to process and store activated

waste from operation of the EDF installations and from

the decommissioning of the first-generation reactors and

of the Creys-Malville NPP.

The construction licence for the facility, cancelled by

the Administrative Court of Lyon on 6th January 2012

was re-granted to EDF on 4thDecember 2014 following

an appeal.

Work on the construction site started again in April 2105

after a four-month phase of contractor remobilisation. The

ongoing works concern the finalising of civil engineering

work, assembly of the electro-mechanical equipment,

installation of the linings in the cells, and painting the

premises.

The suspension of the constructionworkmeans that the

projected commissioning of facility is at least three years

behind schedule. The ICEDAcommissioning authorisation

application file should be submitted to ASN in the first

quarter of 2016 with commissioning planned for 2017

after conducting the prior tests.

ASN carried out two inspections in 2015 to verify the

conditions of resuming work on the construction site

and its management. The results of these inspections

were generally satisfactory. Work on the site resumed

with rigour and the worksite is well managed. The level

of surveillance put in place by EDF is appropriate for

the risks. ASN will remain attentive to the quality of

work performance in 2016 to allow the facility to be

commissioned.

Saint-Laurent-des-Eaux silos (BNI 74)

The installation, which was authorised by the Decree

of 14th June 1971, comprises two silos which are used

to store irradiated graphite sleeves (LLW-LL) from

the operation of the graphite-moderated gas-cooled

500

CHAPTER 16:

RADIOACTIVE WASTE AND CONTAMINATED SITES AND SOILS

ASN report on the state of nuclear safety and radiation protection in France in 2015