Table of Contents Table of Contents
Previous Page  401 / 536 Next Page
Information
Show Menu
Previous Page 401 / 536 Next Page
Page Background

Fire

Following these inspections and with regard to the fire

risk, ASNnotes that the relations between the sites and the

departmental fire-fighting and emergency response services

are on the whole satisfactory and that the organisation of

the response is not generally an issue in themanagement

of actual fires. However, the findings made in previous

years are still valid and concern a majority of the sites

inspected:

the sectoring of premises could be improved in order to

prevent the spread of fire (in particular poor closure of

the doors contributing to fire sectoring and lack of risk

assessment with respect to certain sectoring anomalies); 

deviations linked to the management of fire detection

inhibitions;

deviations in the management of stores of equipment

representing significant heat potential, in particular

during reactor outage phases;

deviations in the use of fire permits.

Problemswith the accessibility of fire-fighting equipment

were once again observed.

The number of outbreaks of fire recorded for 2015 exceeds

that of 2014. On 2nd July 2015, the lack of identification

of the titanium fire risk prior to cutting operations led

to a fire which concerned a part of the condenser of the

Paluel NPP reactor 2.

Explosion

During its inspections, ASNalso assessed the organisation

of the sites for dealing with the explosion risk, including

nuclear safety and worker protection aspects in the

management of this risk.

ASN found that the expertise of the personnel regarding

this question is gradually improving, but considers that

EDF must ramp-up its efforts concerning training and

exercises for the response crews.

Some of the maintenance measures required by the EDF

internal doctrine for pipes carrying hydrogenated fluids

are not always taken (nitrogen tightness test of the double

envelope on certain pipes, daily average estimate of leaks

from the alternator, etc.).

ASN also considers that on all the reactors in operation,

insufficientconsiderationisgiventotheoperatingexperience

feedback concerning events which occurred in 2014 on

theDampierre, Tricastin and Le Blayais sites; it found that

certain compensatorymeasures defined in2014 following

these events have still not been implemented.

Finally, an event of interest in terms of operating experience

feedback occurred on 16th September 2015 in Civaux:

when cutting a pipe, a flame appeared and persisted for

approximately fifteenminutes. The risk of hydrogen leaks

linked to the cutting of this pipe had not been identified

prior to the activity.

Maintenance activities

Concerning the performance of maintenance work, ASN

observes that the number of quality defects found is on the

whole stable. Theworkers still have to deal with constraints

linked to work organisation, insufficient preparation

for certain activities, scheduling changes and problems

withworksite coordination, leading to activity delays or

postponements. EDF has implemented a specific multi-

year action plan designed to reinforce themanagement of

activities scheduled and carried out duringmaintenance

outages of nuclear power generating reactors. Even if

this action plan allows unhurried management of the

preparation and performance phase by the licensee, ASN

considers that EDFmust continue with long-termefforts,

in particular with a view to the operating life extension

of the reactors, the “major overhaul” programme and the

lessons learned from the Fukushima-Daiichi accident,

leading to an increased volume of maintenance activities,

as well as extensive personnel turnover.

With regard to the procurement of spares and equipment

repairs, ASN observed that the shortcomings in the

satisfactory control of these activities, identified inprevious

years, are fewer in number but nonetheless persist.

Delays in the inspections or in incorporating new

maintenance programmes into the documents mean

that deviations or equipment deterioration are detected

belatedly.

ASN also observes differences among the sites in how

the qualification of the equipment for accident operating

conditions is maintained and in the requalification

operations for this equipment.

Finally, ASN considers that the NPPs could improve the

way in which they implement the AP-913 maintenance

method (see point 2.7.1).

Equipment condition

The equipmentmaintenance and replacement programmes,

the periodic safety reviewapproach and the correction of

conformitydeviations shouldmake it possible to check and

ensure the continued ability of the equipment important

for safety in an NPP to perform the functions assigned

to it for protection of the interests mentioned in Article

L.593-1 of the Environment Code.

During the course of its inspections, while still observing

shortcomings in the NPPs’ implementation of and

compliance with the rules issued by the head office

departments for handling conformity deviations, ASN

did see significant progress this year on this subject, with

regard to organisation and in-house training of the persons

involved in this conformitydeviations remediationprocess.

ASNconsiders that the sitesmust continue their efforts, in

particularwith regard to the identification and traceability

of the deviations detected. The potential seriousness of

certaingeneric conformitydeviationsdemonstrates that EDF

401

CHAPTER 12:

EDF NUCLEAR POWER PLANTS (NPPs)

ASN report on the state of nuclear safety and radiation protection in France in 2015