Table of Contents Table of Contents
Previous Page  441 / 536 Next Page
Information
Show Menu
Previous Page 441 / 536 Next Page
Page Background

buildingdesigned tomeet reference earthquake standards)

was once againdelayedbyCEA: the substantialmodification

application file is now being announced by CEA for the

first quarter of 2016. Even if the organisation currently in

place in the facility for monitoring outside contractors is

satisfactory, it will need to be significantly strengthened

in the light of the renovation operations.

Despite the delays in the facility’s renovationproject, CEA

submitted its periodic safety review file inApril 2015. ASN

considered it to be unsatisfactory and requested that it be

supplemented, inparticularwith regard to the conformity

of the equipment necessary in the short term in the light

of the requirements defined by CEA.

ÉOLE and Minerve reactors (Cadarache)

The ÉOLE and Minerve critical mock-ups are very low

power reactors (less than 1 kW) used for neutron studies,

inparticular toqualify calculation systems, evaluate gamma

or neutron attenuation in materials and acquire basic

nuclear data.

The ÉOLE reactor (BNI 42), whose construction was

authorised by the Decree of 23rd June 1965, is intended

for neutron studies of light water reactor cores. It is able

to reproduce a neutron flux representative of that of the

power reactor cores, on a very small scale. The Minerve

reactor (BNI 95), whose transfer from the Fontenay-aux-

Roses research centre to the Cadarache research centre

was authorised by the Decree of 21st September 1977, is

situated in the same hall as the ÉOLE reactor. It is primarily

devoted to effective cross-section measurements.

In 2015, ÉOLE and Minerve continued their teaching

and research activities, inparticularwith the “FLUOLE 2”

programme, for which ÉOLE was authorised to operate

at 1 kW.

The examination of the second periodic safety review led

ASN to issue its resolution of 30thOctober 2014, making

continuedoperation conditional on the removal ofmost of

the nuclearmaterials fromstorage in the near future, along

with a limited improvement in its seismic resistance, no

later than the end of 2017 and then its compliance with

current seismic resistance requirements before the end

of 2019. In 2015, CEA thus transferred a significant part

of the radioactive substances stored in the facility to the

Magenta installation on the Cadarache site, nine months

ahead of the schedule set by ASN, thus achieving a 95%

reduction in the radiological impact of a possible accident.

With regard to the limited seismic resistance reinforcements,

the studies have reached the detailed design stage and

will enable CEA to clarify how it will be carrying out the

reinforcement work before the end of 2017.

Given the cost of the reinforcements to the buildings

that would be needed in order to meet current seismic

resistance requirements, CEA will shut down the facility

at the end of 2019 to comply with the ASN resolution of

30th October 2014.

Irradiation reactors

The Osiris reactor and its ISIS critical mock-up (Saclay)

The Osiris pool-type reactor (BNI 40) has an authorised

power of 70 megawatts thermal (MWth). It is primarily

intended for technological irradiationof structuralmaterials

and fuels for various power reactor technologies. It is also

used for a few industrial applications, in particular the

production of radionuclides for medical uses, including

molybdenum-99 (99Mo). Its critical mock-up, the ISIS

reactor, with a power of 700 kWth, is essentially used for

trainingpurposes today. These two reactorswere authorised

by a Decree dated 8th June 1965.

Owing to the significant design differences between this

older facility and the best techniques currently available for

protection against external hazards and the containment

of materials in the event of an accident, 2015 was the last

year of operation for the Osiris reactor. The ISIS reactor

will be able to continue to operate until 2019.

The various inspections showed that the facility is operated

in satisfactory conditions. Application of the regulatory

provisions concerning nuclear pressure equipment was

improved.

The main cause of most of the significant events in 2014

was hardware failures, in particular in instrumentation

and control. They had nomajor safety impact. A number

of residual studies from the 2009 periodic safety review

underwent complementary analyses, in particular with

regard to the handling conditions for the Orphée spent

fuel stored in the facility. The handling conditions for these

fuels weremademore robust in order to improve control

of the criticality risk.

ASN inspection in the core of the shutdown Masurca reactor, April 2015.

441

CHAPTER 14:

NUCLEAR RESEARCH AND MISCELLANEOUS INDUSTRIAL FACILITIES

ASN report on the state of nuclear safety and radiation protection in France in 2015