Table of Contents Table of Contents
Previous Page  444 / 536 Next Page
Information
Show Menu
Previous Page 444 / 536 Next Page
Page Background

In addition, even though ASN notes that a large share of

the undertakings made for the periodic safety review of

the facility in 2009 have beenmet, a number of particular

technical justifications have yet to be produced.

In the follow-up to the Fukushima Daiichi accident, the

ASN resolution of 8th January 2015 set the requirements

for the facility’s “hardened safety core”, which is the only

one of the CEA batch 2 facilities for which the need to

deploy such a hardened safety core was identified by

the licensee.

Test reactors

Cabri reactor (Cadarache)

The Cabri reactor (BNI 24), created on 27th May 1964,

is used for experimental programmes aimed at better

understanding nuclear fuel behaviour in the event of

a reactivity accident. The reactor is operated by CEA.

Modifications to the facility were authorised in a Decree

of 20th March 2006, in order to run new research

programmes. The reactor’s sodium loop was replaced

by a water loop in order to study the behaviour of high

burn-up fraction fuels in accident situations representative

of those that could be encountered in a pressurisedwater

reactor.

2015 was marked by the first criticality of the modified

reactor, authorised for start-up tests by ASN on

13thOctober 2015. In order to authorise this criticality,

ASN in particular examined:

the implementation of the prescriptions of the ASN

resolutionof 8th January 2015 concerning integrationof

the lessons learned fromtheFukushimaDaiichi accident;

the completion of CEA’s 2004 commitments prior to

criticality, as part of the facility’s safety reassessment and

the modification project authorised in 2006;

the completion of CEA’s  2008 and  2009 commitments

for refuelling of the driver core;

updating of the facility’s baseline requirements, in

particular the safety analysis reports and the general

operating rules transmitted in February  2015;

implementation of compensatory measures following

the significant event of 15thDecember 2014 concerning

a fault in the core system.

The three inspections carried out by ASN in 2015,

devoted to the start-up tests and the periodic checks

and tests, did not reveal any significant deviation with

respect to the facility’s baseline safety requirements. CEA

will be required to conduct a more detailed analysis of

the numerous events which occurred at first criticality.

On 13th October 2015, ASN also prescribed the

transmission of additional files, including a report

summarising the commissioning tests prior to the first

experimental test. In it, ASN also notifies the deadline

for the next periodic safety review of the facility in 2017.

Phébus reactor (Cadarache)

The Phébus reactor (BNI 92), the creation of which was

authorised by the Decree of 5th July 1977, enabled tests to

be performed concerning the severe accidents that could

affect pressurisedwater reactors. It was finally shut down

in 2010 following the “fission products” experimentation

programme which started in 1988. CEA informed ASN

in 2013 that it intended to shut down this BNI once and

for all and in 2014 transmitted an updated file presenting

the decommissioning preparation operations and the

decommissioning plan. In 2015, CEAwas authorised to

begin the first operations to prepare for decommissioning,

in this case the disassembly of cooling equipment outside

the reactor building. CEA undertook to submit the

decommissioning file for the facility no later than 2017.

It will also submit the facility’s periodic safety review file.

ASNaskedCEA to supplement its decommissioning plan

and its safety review orientations file with respect to the

management of radioactive substances.

Installation of biological shielding in the Cabri research reactor containment, 2012.

444

CHAPTER 14:

NUCLEAR RESEARCH AND MISCELLANEOUS INDUSTRIAL FACILITIES

ASN report on the state of nuclear safety and radiation protection in France in 2015